Upgrading your connection? Check what fits in 3×80 A first
Start by checking what fits within your connection. With load balancing, you share the available budget across several charge points. A DC charger can also fit within 3×80 A. Because of grid congestion, upgrading beyond that limit is not a realistic next step in many places: waiting lists can take years, and some are closed.
Eight AC charge points on one connection
The Crailo charging hub has more than twenty charge points on twelve dual-socket chargers. Since March 2026, WIM has used load balancing to share the power across eight of them, split over two 80 A connections. The chart below is a worked example of one connection with eight charge points and three cars charging.
8 charge points on 80 A, three cars charging
Worked exampleFixed spliteach charge point 10 A
30 A of 80 A in use
With WIM Load Managementspare power goes to the cars that are charging
80 A of 80 A in use
So the number of charge points is not the same as the number of cars that can charge at full power at once. When they all charge, they share the budget. Load balancing does not make your connection any bigger. We work out how many charge points fit at your site during the intake.
How much of your connection does a charge point need?
Worked example: power ≈ amps × 230 V × 3 phases. On that basis, a 3×80 A connection delivers about 55 kW. The values below are rounded and assume three-phase charging.
| Charger or connection | Power | Current per phase |
|---|---|---|
| AC 11 kW | ≈ 11 kW | ≈ 16 A |
| AC 22 kW | ≈ 22 kW | ≈ 32 A |
| DC 30 kW | ≈ 30 kW | ≈ 43 A |
| Whole connection 3×80 A | ≈ 55 kW | 80 A |
That 55 kW is not automatically your charging budget: your building uses power too, so you set the chargers’ budget to allow for that. A 30 kW DC charger also fits within 3×80 A: that is about 30,000 / 690 = 43 A per phase. DC chargers from Alfen, Ekoenergetyka and Alpitronic, among others, work with load balancing.
Connection full? These are your options
Up to and including 3×80 A, you count as a small consumer, and in principle the grid operator may not refuse such a connection. Above 3×80 A, it becomes a large-consumer connection with contracted transport capacity. In large parts of the Netherlands the grid is full. There, you join a waiting list for more capacity; some lists are closed, others take years. The Netbeheer Nederland capacity map (in Dutch) shows whether there is a queue in each area. WIM cannot solve that limit.
-
Load balancing within your budget
Share the power between the cars that are charging. Unused charge points do not hold back any power.
-
Meter module on your main connection
The charging budget follows your building's load. You get the price during the intake.
-
Battery as a buffer, not through WIM
A battery can step in at busy times, so the chargers together can draw more than the connection alone supplies. WIM does not supply or control batteries. This is a separate investment, through a battery supplier or your installer.
-
Upgrading beyond 3×80 A
Often means a waiting list. Ask your grid operator what is possible at your location.
What does load balancing with WIM require?
WIM divides a fixed budget per connection via OCPP, so you do not need a meter in the meter cupboard. Your chargers must be online, support OCPP 1.6 with charging profiles and apply those profiles correctly. You can mix makes, for example Alfen (AC and DC), go-e, Easee, Ekoenergetyka, Vestel and Alpitronic. Zaptec chargers can be managed, but not load balanced.
We always start with an intake, in which we look at your connection, chargers, firmware, settings and internet connection. Also read Is my charger suitable for WIM?.
Load balancing is an add-on to WIM Management. Without a meter module, you pay:
- €2.50 per charge point per month excl. VAT.
- At least €25 per location per month excl. VAT.
- €149 one-off per location excl. VAT, covering the intake, testing and setup.
WIM Management itself is priced separately on the pricing page.
What if the connection drops?
Each charger falls back to a fixed basic profile, and together those profiles fit within your connection. Read how the four safety nets work.
Want to know what fits within your connection? Give your number of charge points, the makes and your connection size in the contact form. That starts the intake.
By WIM Energy B.V. · Updated